S106 well is an exploration well of Talimuxiang
structure in Shaya uplift in Talimu basin ,where salt-gypsum
bed is thick and buried deeply. In the influence of high
temperature and high pressure ,many complex problems are
happened in the drilling of salt-gypsum bed in S106 well ,
such as lost circulation ,lost drilling tool ,sidetrack and so on .
Through analyzing the above problems ,the drilling technique
of salt-gypsum bed in the area is discussed ,and the drilling
difficulty is solved.