超高压射孔-油井增产措施联作完井技术
石油钻采工艺
2000年 22卷 第6期
阅读:76
查看详情
Title
WELL COMPLETION TECHNOLOGY ASSOCIATE WITH OVER-HIGH PRESSURE PERFORATION AND OIL WELL STIMULATION
Authors
Wang Yuanming
Chen Yuxiang
单位
河南石油勘探局采油二厂, 河南唐河 473400
中国矿业大学, 北京 100083
摘要
超高压射孔技术可与酸化、压裂技术联作,用于灰岩及低压、低渗油藏,降低操作费用,提高采油指数;与防砂技术联作用于疏松砂岩油藏,可减少污染,改善防砂效果。从16口超高压射孔完井的压力恢复曲线统计可知,14口井的表皮系数为负值。
Abstract
Well completion technology associate with over-high pressure perforation and oil well stimulation is a new technology developing in abroad. The basic theory and the status of the technology are narrated. The process of the operation is introduced. The over-high pressure perforation technology can associate with acidizing or fracturing, which can be used in carbonate reservoir and low pressure and low permeability pools. The technology can reduce operation fare and improve productivity index. The over-high pressure perforation technology also can associate with sand control technology, which can be used in unconsolidated sandstone reservoir. This technology can reduce pollution and improve sand control effects. From the pressure buildup curve of 16 wells who used over-high pressure, the skin factor of 14 wells is negative.
Keywords:
high pressure;
perforation;
fracturing;
acidizing;
well completion;
DOI
10.3969/j.issn.1000-7393.2000.06.019