论文详情
亚肯3井深井侧钻技术
石油钻采工艺
1996年 18卷 第3期
阅读:71
查看详情
Title
DEEP WELL SIDETRACKED TECHNOLOGY OF YAKEN-3 WELL
Authors
Yang Jinyuan
Deng Xingde
Pan Weiguo
Geng Baohe
单位
塔里木勘探开发指挥部钻井研究大队
华北油田钻井研究所
摘要
塔北亚肯3井设计井深6200m,钻至5546.33m时发生盐层卡钻,处理事故中钻具又折断,被迫填井侧钻。第一次侧钻因螺杆钻具事故而失败。第二次侧钻,侧钻点井深5100m。在井深、温度高(实测112℃)、压力高(钻井液密度1.74g/cm3)、地层可钻性差、工具面不易控制的情况下,采用螺杆钻具和有线随钻测量技术侧钻成功,并将?177.8mm尾管安全下至井深5656.73m。
Abstract
Design depth of Yaken-3,in North Talimu,is 6200 meters,while drilling to 5546.33 meters,the strick is happened in salt.The drill collar is broken in treating.So the sidetracked is started.The first sidetracked is failure because of downhole motor.The second kop is selected in 51 00 meters.Under deep well,high temperature(112℃),high pressure(drilling fluid density is 1.74g/cm3),poor drillability,it is successful to sidetracked using downhole motor and SST tool.It is successful to send the177.8mm liner to 5658.73 meters.
关键词:
塔里木盆地;
深井钻井;
钻井事故;
侧钻;
钻具组合;
钻井参数;
Keywords:
Talimu Basin;
deep drilling;
drilling accident;
sidetracked;
hottom hole assembly;
drilling;
DOI